單項選擇題

PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.

A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish


最新試題

The inputs of developing project management plan do not include()

題型:單項選擇題

The() defines the phases that connect the beginning of a project to its end.

題型:單項選擇題

The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

題型:單項選擇題

()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

題型:單項選擇題

()means that every project has a definite beginning and a definite end.

題型:單項選擇題

Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

題型:單項選擇題

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

題型:單項選擇題

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

題型:單項選擇題

Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

題型:單項選擇題

Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()

題型:單項選擇題