單項選擇題

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

A.Project managers
B.Project team members
C.Sponsors
D.Project stakeholders


你可能感興趣的試題

1.單項選擇題

The() defines the phases that connect the beginning of a project to its end.

A.schedule
B.project life cycle
C.temporary
D.milestone

2.單項選擇題

()means that every project has a definite beginning and a definite end.

A.Project phase
B.Unique
C.Temporary
D.Closure

3.單項選擇題

() is one of the quality planning outputs.

A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist

4.單項選擇題

The inputs of developing project management plan do not include()

A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes

5.單項選擇題

Which of the following statement related to PMO is not correct?()

A.The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.
B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
C.The PMO focuses on the specified project objectives.
D.The PMO optimizes the use of shared organizational resources across all projects.

最新試題

Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

題型:單項選擇題

In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

題型:單項選擇題

空白(2)處應選擇()

題型:單項選擇題

Which of the following statement related to PMO is not correct?()

題型:單項選擇題

The()provides the project manager with the authority to apply organizational resources to project activities.

題型:單項選擇題

()is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.

題型:單項選擇題

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

題型:單項選擇題

Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

題型:單項選擇題

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

題型:單項選擇題

Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()

題型:單項選擇題